Pages
Questions: Click Here
Preguntas: Presione aquí
Or Call the Hotline
O Llame la Línea directa telefónica:
1-855-33HOLLY
(1-855-334-6559)
Here is your regular scheduled update from the Holly Plant Decommissioning Project Team:
The TRC, LVI, and Austin Energy team have continued to remove steel and piping from Holly Unit 3. This week’s post details, through the following series of images, the team starting to remove piping and steel components from the boiler structure on Unit 3 now that all asbestos abatement activities have been completed on the unit.
This is a view of the Holly 3 boiler prior to the team starting asbestos abatement activities on Holly Unit 3.
This view shows the boiler being draped with plastic sheathing. The team enclosed the areas where asbestos was removed.
In this view, you can see Holly 4 on the left and Holly 3 next to it with portions of the plastic sheathing removed. The demolition team removes the plastic sheathing when they finish removing the asbestos in the current work areas. Lastly, you can see Holly Units 1 and 2 that were adjacent to unit 3 have been previously removed by the team.
A view of the east or right side of the Holly 3 boiler shows the scaffolding used to assist the demolition team in removing the asbestos.
Workers begin to dismantle the scaffolding used on Holly Unit 3.
The following image shows Holly Unit 3 boiler ready for dismantling. The team finished removing all the asbestos and plastic sheathing. In the far left, Holly 4 boiler is immediately behind Holly 3.
Welders begin to cut the lower portion of the boiler. The demolition team will work upwards until the entire boiler is removed.
A welder cuts a portion of a boiler water tube panel.
Two welders begin cutting another boiler wall panel.
The demolition team continues to cut the left side of the boiler furnace. Notice, the team’s progress in removing the lower portion of the boiler.
Welders are cutting another boiler wall panel.
Workers at the top of the boiler structure continue to remove smaller pieces. These pieces are loaded into a basket and lowered to the ground.
In this view, you can see the progress made by the team in removing the bottom of the boiler. One of the cut wall panels is resting along the right side of the boiler structure and will be moved to the scrap yard.
Welders continue to cut their way up the boiler wall panels. Another worker sprays water over the bottom of the area to keep dust contained and extinguish the hot metal slag.
This is a view looking inside and up towards the top of boiler furnace from the bottom. At the top of the image, you can see the superheater tubes and a wall of tubes that split the furnace into two halves.
This is a view of the opposite side of the furnace highlighting four of the twelve burners that were used to heat the boiler wall tubes inside the furnace.
This is the current view of the Holly 3 boiler from the bottom of the boiler structure.
Lastly, more images can be found in our image gallery. Click Here.
Here is your regular scheduled update from the Holly Plant Decommissioning Project Team:
Demolition activities continue throughout the plant. In the following series of images, you will see the joint Austin Energy, TRC, and LVI team continue to remove piping and steel components from the boiler structure on Unit 4. This is a continuation of the update highlighted in the January blog.
This is a view of the Holly 4 boiler when the demolition team was removing the stack.
The following image highlights the team’s progress on the Holly 4 boiler. The team has removed additional boiler wall panels which allow viewers to see through the structure.
This view of the boiler structure which the exposed concrete floor at the very top. The team has completed removing the upper portion of the boiler structure.
The image highlights the red steam drum vessel and the concrete floor right above it.
The welders finished cutting the steam drum which will be removed in pieces after the rest of the team has removed the concrete floor.
A worker operates the portable jack hammer which is cracking the concrete floor. Pieces of the floor drop all the way down to ground level. The team will gather and remove the concrete pieces.
In this image, you can see that a quarter of the concrete floor on the upper right side of the boiler structure has been cracked and eliminated.
At ground level, you can see the concrete pieces that have fallen and accumulated underneath the boiler structure.
Looking up from ground level where the boiler furnace used to reside, you can see that the team has left in place only the supporting steel beams. At the very top of the structure, you can see the red steam drum hanging from the structure.
Looking at the lower third of the following image and towards the top of the boiler structure, you can see a portion of the red wind box that brought combustion air into the furnace. At the very top, there still remains a portion of the concrete floor that will be removed by the demolition team.
In this image looking towards the top of the boiler structure, you can see a portion of the bottom of the air preheater has been exposed. The team will begin to remove the baskets forming the circular part of the preheater.
In this view of the entire boiler structure, you can see that the team has removed more of the concrete floor at the top and only a small portion on the left side still remains to be removed.
In this view of the top floor of the boiler structure, the team has removed the entire concrete floor exposing the bare steel beams. The steam drum with a circular man hole opening is on the right side of the structure just below the top floor.
This is the latest image of the Holly 4 boiler structure. The boiler furnace and its wall panels that comprised the right half side of the structure have been removed exposing the steel structure with daylight coming around the remaining beams. On the far left side towards the top of the structure, a portion of the air preheater is still in place. You can see the team’s progress by comparing this image to the first one in this blog.
Lastly, more images can be found in our image gallery. Click Here.
Here is your regular scheduled update from the Holly Plant Decommissioning Project Team:
The TRC, LVI, and Austin Energy team have continued and completed removing one half of the turbine generator building. This week’s post details, through the following series of images, the latest view of the team removing one half of the turbine generator building that housed the four steam turbines and electric generators.
Working on the east end of the turbine generator building, a welder prepares to remove a steel beam.
With the beam being held by the overhead crane, the welder makes a cut to clear it from the supporting structure.
The beam is lifted and moved to the scrap yard.
The demolition team removed the beams and roof covering the truck bay on the east end of the building. In the middle of the image, you can see a section of the roof has been removed by the team.
A welder cuts the opposite end of the roof section.
The team is cutting the building roof width wise at every fourth column. Notice the gap that appears in the roof in the middle of the image. This indicates the steel that has been cut and removed by the demolition team in preparation for pulling the building section to the right of the gap.
An excavator is set up with cables attached to the building section.
The excavator pulls on the cables causing the building section to collapse forward.
The demolition team has completely removed the building section and the concrete floor is ready to be removed.
This image shows the collapsed building section over the concrete portion of the remaining structure. Also, Holly 3 is in the background on the left. Lastly, you can see there are still two sections of the turbine generator building that still need to be removed by the demolition team.
Notice, day light is now entering the turbine hall. The demolition team has finished lowering the steel columns and left them on the concrete floor, as seen in the background towards the middle of the image. The photographer took the image from the interior of the turbine generator building and facing east.
In similar fashion as described previously, the team uses the excavator to bring down the second section of the building.
The excavator grabs and pulls portions of the building off of the turbine hall concrete floor.
In the lower middle of the following image, a welder cuts one of the steel columns. The rest of the demolition team is preparing to pull the building section down over the concrete floor.
With cables attached to the middle columns at the top, the excavator pulls on the cables and the building section begins to tilt forward. A water truck is parked in the middle ready to spray water on the collapsed roof debris to contain the dust particles.
The building is quickly coming down and is half way towards landing on top of the concrete floor.
The building section is now totally collapsed over the concrete floor. The demolition team is ready to remove the debris and the steel structure.
Compare the following image to the last image in the previous week’s blog. Holly 3 is on the far left. However, you can see that only half of the turbine generator building is still standing. The remaining part of the building structure is adjacent to Holly 3 and Holly 4.
Lastly, more images can be found in our image gallery. Click Here.
Here is your regular scheduled update from the Holly Plant Decommissioning Project Team:
Demolition activities continue throughout the plant. In the following series of images, you will see the joint Austin Energy, TRC, and LVI team start to remove turbine generator building that housed the four steam turbines and electric generators.
This image is of the south wall of the turbine generator building before the demolition team began any major cutting of the walls. The Holly 3 boiler is on the left side of the image.
Two workers on lifts begin to cut the steel siding on the south wall of the building. The elevator shaft that was between the Holly 1 and 2 units and rising past the roof is still in the center of the image.
A worker operating the shearer begins to cut the steel columns that formed the elevator shaft.
The shearer moves to the right and begins pulling on the steel columns.
The steel column collapses and half of the shaft structure begins falling.
The entire elevator shaft structure begins to tilt downward as the shearer pulls the columns.
A worker operating the excavator now approaches the shaft from the left side.
The excavator pulls the last remaining portion of the elevator shaft. A worker continues to spray water to keep dust particles from becoming air borne.
The south wall of the building is beginning to disappear as the demolition team removes more sections of siding. The Holly 3 boiler is on the left side of the image. On the right side of the image, the team is beginning to remove the roof at the end of the building.
Workers, on top of the right side or east end of the building, are cutting the roof panels. The wall siding has been removed by the demolition team. The roof and walls cover the east end truck bay. Additionally, one of the electric generators is still in the truck bay.
The demolition team continues to remove wall siding from the north side of the building. Workers, on the right side of the image behind the excavator, are on lifts removing siding as they work their way down the side of the building. The excavator at the front is pulling siding panels opening the walls of the building.
Welders continue to cut and remove the roof panels exposing the roof to the structural steel columns that surround the building.
On the south side of the building, the excavator is used to pull more of the wall siding down to the ground.
The excavator tears down the yellow brick siding that appears between the steel columns.
The demolition team tore off the yellow brick siding which is now dropped to the ground.
A welder cuts one of the steel roof beams on the east end of the building.
The crane lifts and moves the steel beam to the scrap yard.
This is the current view of the turbine building looking in the direction where Holly units 1 and 2 used to stand. The opening in the center of the image will be expanded to allow the shearer and excavator to enter the lower floors of the turbine building and remove all of the remaining equipment.
Lastly, more images can be found in our image gallery. Click Here.
Here is your regular scheduled update from the Holly Plant Decommissioning Project Team:
Demolition activities continue throughout the plant. In the following series of images, you will see the joint Austin Energy, TRC, and LVI team completely remove the Holly 1 & 2 control room building. This week’s post brings you the latest update on what has happened to the Holly 1 and 2 control room structure.
This image shows the right side of the control room building with glass windows facing the plant grounds in the center. On the right side of the image, you can see it is attached to the steam turbine generator building.
This image shows the left side of the control room building. This image also highlights the team’s accomplishment in removing the Holly 2 boiler.
The shearer begins removing the wall on the left and front sides of the control room building.
The demolition team completed removing all the glass windows from the front of the building.
This image highlights the control room on the right side of the building on the upper floor. This floor was where the operators controlled boiler operations.
The shearer grabs and pulls on the floor beams bringing down the front of the building and floors.
In the top center of the image, you can see the rear part of the control room with one of the control panels. The glass door to the left of the control panel led to the steam turbine generator floor.
The shearer on the right side of the image grabs and begins to pull one of the floor beams.
As the shearer pulls on the beam, the rear part of the building begins to come down. A worker on the right maintains a spray of water to keep dust particles under control.
The building continues to fall with the last of the control room panels.
The team uses the shearer for a final pull to bring down the remainder of the control room floor.
Compared to our first image, you can see that the building is gone. The team will demolish the remaining bottom concrete floor.
As the team removes the remaining debris, you can begin to see a large opening into the turbine hall in the left of the image.
This is a view of the turbine hall. The floor openings is the location of the now removed Holly 2 steam turbine. In the center towards the right, you can see the large opening left by the removal of the Holly 1 & 2 control room building. The stairwell in front of the opening led to the control room floor.
The demolition team uses the portable jackhammer to cut the remaining concrete walls into sections. The welder on the right is cutting the concrete rebar.
The team pulls the wall sections one by one until the floor is brought down.
This view highlights the team’s progress in removing the turbine control building.
This is the current view of the turbine control building with Holly 3 and 4 in the background. In this image, you can see the team has demolished the bottom concrete floor.
Lastly, more images can be found in our image gallery. Click Here.