Regarding Noise Near the Holly Plant Area ..

On December 10, 2011, in Uncategorized, by admin

We recently had someone submit a question through our “Contact Us” page about the  the noise is that is emanating from the power plant area.

The noise you hear is from work that the city’s Water and Waste Water Department is performing next to the park in order to remove the lift station that has been there for years and at times providing a foul odor to the neighborhood. The work will be completed by the end of December and the lift station will be gone forever along with the smell. There are currently no activities inside the power plant that are emanating any loud noise that you could hear from your home near the Holly Plant Area.

Austin Energy and TRC will notify the neighborhood in advance during the plant removal activities of any unusual sounds you may hear from the work that will be performed.

 

Tagged with:
 

FAQ

On October 5, 2011, in , by admin

Frequently Asked Questions:

 

1. When will the project start?

October 2011

2. When will the project end?

April 2013

3. What is the project timeline?

Holly Decommissioning Project Timeline over 18 months

Holly Decommissioning Project Timeline over 18 months

4. What percentage or what time frame will be dedicated to the “asbestos removal” portion of the plan? Is it during the entire 18 months or only during a certain phase of the project?

Approximately 5 months will be dedicated to asbestos removal and the removal will begin in January and last until July of 2012.

5. Are there any plans by the company who has the contract for Holly Street to sell any of the equipment inside the plant before it is demolished, such as the smaller items like lighting fixtures, work benches, storage cabinets, factory carts and things of that nature?

Under the contract terms that Austin Energy signed with TRC (the City of Austin awarded demolition contractor), TRC owns all of the equipment and materials and nothing will be left in Austin Energy’s possession for disposal. In the event TRC decides to sell some of the smaller items in the Austin area, we will notify the public.

6. Once demolition begins, will the hike and bike trail be rerouted?

The trail will remain in place as is until demolition is completed, then a newly added trail along the plant’s shoreline will reconnect with the existing shoreline trail.

7. What is the plan for the land that the power plant occupies? Park? Housing?

The land that will be left after the four power plant units are removed will remain as Austin Energy property.  A fence surrounding this area as well as the switchyard to the North, the substation on the west, and the adjacent statcom facilities will be constructed after the demolition and all remediation activities have been completed.  This area is required by Austin Energy to maintain the energized electrical facilities and infrastructure that will continue to supply power to the downtown area and other parts of the city.

Click Picture to enlarge:

Land Use after Holly Plant removal
8. Will the portion of the trail near the plant be kept open for group walking or running events during demolition?

Yes it will be kept open during the entire time the plant is being demolished. At no time will the trail be closed. During working hours there will be flaggers that will momentarily stop any joggers or bicyclists where the trail crosses the haul road going into the plant if a truck is approaching the trail crossing.

9. Why are there trucks going up Mildred instead of Pedernales like was stated before?

The trucks going up Mildred are removing material from the Canterbury lift station, a water and waste water project. Truck traffic associated with the Holly Plant removal will only travel on Perdenales and Cesar Chavez streets.

Tagged with:
 

Project Timeline for Holly Plant

On October 5, 2011, in Uncategorized, by admin

Here is a project timeline for the Holly Plant:

Timeline for Holly Plant Decommissioning Project

Timeline for Holly Plant Decommissioning Project

Work will begin October 2011 and finish April 2013.

Tagged with:
 

Holly Plant: Construction

On September 22, 2011, in , by admin
(Presione el imagen para ver en español)

 

Tagged with:
 


“Meet The Contractor”

Join Austin Energy, TRC, LVI, and other contractors at our upcoming meeting:

Tuesday, September 20, 2011 at 5:30 p.m.

Metz Elementary School • 84 Robert T. Martinez, Jr. Street

•Light refreshments provided

Photo from "Meet the Contractor" Meeting of Holly Power Plant Decommissioning Project

“Meet the Contractor” Meeting of Holly Power Plant Decommissioning Project

Click here to view the presentation:  Part 1 and Part 2 

 